Business EnvironmentHybridHardECO: Business Environment Task 2.2

PMP Practice Question: Business Environment — Hybrid, Hard

Your organization is executing a hybrid project to modernize its supply chain platform. The architecture team is working predictively on core system integration (9-month timeline), while feature teams work in 3-week iterations on user-facing capabilities. A recent market analysis reveals that customer expectations for real-time shipment tracking have shifted dramatically due to new market entrants. The product backlog contains tracking features, but they're prioritized for release 3 (month 10). The architecture team indicates that exposing real-time data externally requires additional security infrastructure not in the current plan. Your sponsor asks for options to respond to the market shift. What is your best recommendation?