PMP Practice Question: Business Environment — Hybrid, Easy

A healthcare organization is implementing a patient portal system using a hybrid approach. The database and security infrastructure are being deployed predictively, while user interface features are developed in sprints. Three months into the project, the organization announces a merger with another hospital network. The project sponsor asks the project manager to assess how this merger might impact the project. Several stakeholders from the merging organization have different technology platforms and patient management processes. What should the project manager do next?