PMP Practice Question: Business Environment — Agile, Hard

Your organization is undergoing a digital transformation, and you are leading an agile product development team creating a customer-facing mobile application. During Sprint Planning, the CFO unexpectedly announces a company-wide 20% budget reduction effective immediately due to declining market conditions. The Product Owner wants to continue with all planned features, while several team members suggest switching to a predictive approach to 'control costs better.' Your current sprint has just started, and you have a potentially shippable increment from the previous sprint. What should you do first to address this business environment change?