Your construction project is building a manufacturing facility in an emerging market. Six months into the 24-month schedule, the host country implements new environmental regulations requiring additional emissions control systems not included in your original scope. Compliance will add $3.5M to the $28M budget and extend the schedule by four months. However, your contracts with the client contain a clause stating that regulatory changes are the client's responsibility. The client's legal team argues that these regulations were proposed (but not enacted) before contract signing, so you should have anticipated them. The client refuses to approve a change request and demands you absorb the costs. Senior management wants to maintain the client relationship for future opportunities worth an estimated $200M. What should you do?