PeoplePredictiveMediumECO: People Task 2.3

You are managing a construction project that is entering the execution phase. During resource planning, you identified that three specialized technicians are needed for a critical phase starting in six weeks. Your functional manager has just informed you that due to competing organizational priorities, only two of the three requested technicians will be available. The project baseline assumed all three resources would be available, and this shortage will likely extend the project schedule by two weeks. What should you do next?