PMP Practice Question: People — Predictive, Medium
You are managing a construction project that is entering the execution phase. During resource planning, you identified that three specialized technicians are needed for a critical phase starting in six weeks. Your functional manager has just informed you that due to competing organizational priorities, only two of the three requested technicians will be available. The project baseline assumed all three resources would be available, and this shortage will likely extend the project schedule by two weeks. What should you do next?
Study this topic
- 📖Mastering Conflict Resolution Scenarios for PMP Success
Learn proven conflict resolution techniques and navigate realistic PMP exam scenarios. Master the Thomas-Kilmann model and modern collaborative approaches.
- 📖Mastering Negotiation: The Project Manager's Strategic Skill
Negotiation is critical for PMP success—from stakeholder management to resource allocation. Learn proven techniques aligned with PMBOK 8th Edition principles.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More People Questions
View all →You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
A cross-functional agile team is preparing for their next sprint. During sprint planning, the QA specialist expresses concern that the team has been committing to user stories without adequately considering testing effort. She feels that her input is often sought too late in the process, after developers have already estimated and committed to stories. This has resulted in quality issues and testing becoming a bottleneck in the last two sprints. The team wants to improve but is unsure how to better integrate QA perspective earlier. What should the team do?
Your organization is piloting agile practices within traditionally predictive portfolios. You're leading a hybrid project with a co-located agile team and distributed predictive workstreams across three continents. After four months, you notice the agile team has strong cohesion and high performance, but the distributed predictive teams report feeling disconnected and undervalued. Several key resources from the predictive workstreams have requested transfers, citing lack of engagement. Executive stakeholders are questioning whether the hybrid approach is sustainable. What is the MOST effective way to address this disparity?