PMP Practice Question: Business Environment — Hybrid, Easy

A project manager is leading a digital transformation initiative for a retail organization using a hybrid delivery approach. The marketing website will be developed iteratively in two-week sprints, while the backend inventory integration follows a waterfall methodology due to regulatory compliance requirements. During a steering committee meeting, executives express concern about having two different status reporting formats. How should the project manager address this concern?