PMP Practice Question: Process — Predictive, Medium
Your software development project is following a predictive lifecycle with detailed upfront planning. You are currently in the execution phase, and the project is on schedule and within budget. A key stakeholder who was minimally involved during planning now requests a significant feature addition that would provide substantial business value but was not included in the original scope. The stakeholder insists this feature is critical and should be added immediately without formal approval processes. What is the most appropriate action?
Study this topic
- 📖Scope Management: Defining and Controlling What Your Project Delivers
Master scope management techniques that prevent scope creep, ensure stakeholder alignment, and deliver exactly what your project commits to achieve.
- 📖WBS Work Breakdown Structure: Proven Best Practices
Master the essential techniques for creating effective Work Breakdown Structures that drive project success and align with modern delivery approaches.
- 🗂️Flashcards: Risk Responses, Reserves & Contract Types
14 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?