PMP Practice Question: Process — Predictive, Medium

During the planning phase of a pharmaceutical research project, you are developing the project schedule. Several senior researchers insist that certain experimental activities cannot have their durations estimated accurately because the outcomes are uncertain. However, your management wants a detailed schedule with specific milestones for board reporting. The contract includes penalty clauses for late delivery. How should you address duration estimating for these uncertain activities?