A financial services company is implementing a new customer portal using a hybrid approach. The predictive portion involves infrastructure setup and regulatory compliance documentation, while the adaptive portion covers user interface development with two-week iterations. During sprint planning, the infrastructure team reports they need three additional weeks to complete security certifications before the development team can begin integration testing. The project manager is concerned about the impact on the overall timeline. What should the project manager do first?