PMP Practice Question: Business Environment — Hybrid, Easy
A technology company is running a hybrid project to develop a new mobile application. The backend infrastructure is being built using a predictive approach with formal phase gates, while the frontend features are developed in two-week sprints with continuous customer feedback. During a project review, a senior manager questions why the teams are working at different paces and suggests synchronizing all work to monthly milestones. What is the best way for the project manager to address this concern?
Study this topic
- 📖Change Management Across Agile and Predictive Approaches
Master how change management differs between agile and predictive project approaches for the PMP exam. Learn practical techniques for handling change in hybrid environments.
- 📖Governance Frameworks and PMO for the 2026 PMP Exam
Master governance frameworks and PMO structures for the 2026 PMP exam. Learn how organizational governance connects to the expanded Business Environment domain.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Business Environment Questions
View all →A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The predictive phase involves infrastructure setup and data migration, while the adaptive phase covers user interface customization based on feedback. During planning, the sponsor asks how benefits will be measured throughout the project lifecycle. What should the project manager do to align with organizational benefit realization?
A project manager is working on a hybrid project to modernize a legacy billing system. The organization has a strong compliance department that requires detailed documentation for audit purposes. The adaptive team members express concern that creating comprehensive documentation conflicts with agile principles. What should the project manager do to balance these competing demands?
A project manager is leading a hybrid project to launch a new e-commerce platform. The infrastructure deployment follows a predictive approach, while feature development uses Scrum. During a retrospective, the Scrum team reports frustration that infrastructure dependencies are blocking their work. The infrastructure team says they are following their plan and cannot accommodate unplanned requests. What should the project manager do?