PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 2.5

PMP Practice Question: Process — Predictive, Medium

You are managing a construction project to build a new office building. During the execution phase, a key supplier notifies you that the specialized steel components will be delayed by three weeks due to manufacturing issues. The critical path includes the steel frame installation, and this delay will impact the project completion date. Your project sponsor is very concerned about meeting the contractual deadline. What should you do first?

← All questions

Study this topic