PMP Practice Question: Business Environment — Hybrid, Medium

A project manager is leading a hybrid infrastructure upgrade project for a healthcare provider. The network infrastructure follows a predictive approach due to dependencies and vendor contracts, while the application layer uses iterative development. During a governance review, stakeholders express concern that they cannot see integrated progress across both workstreams. The traditional Gantt chart shows infrastructure milestones, but the development team uses a Kanban board. Senior leadership requests a unified view of project health and progress. How should the project manager address this need?