PMP Guide — Empowering Project Managers
ProcessPredictiveEasyECO: Process Task 1.6 - Plan and manage quality

PMP Practice Question: Process — Predictive, Easy

Your manufacturing project has been running for three months. During a quality inspection, you discover that 15% of the produced components do not meet the specifications defined in the quality management plan. Production is continuing, but you are concerned about the trend. What should be your immediate course of action?

← All questions

Study this topic

PMP Practice Question — Process · Easy | PMP Guide