PMP Practice Question: Business Environment — Hybrid, Medium

A retail organization is executing a hybrid project to modernize its supply chain system. The enterprise architecture components follow a stage-gate process, while customer-facing dashboards are developed using Scrum. The organization's PMO requires monthly status reports with earned value metrics for all projects. The Scrum team objects, stating that velocity and burndown charts are more meaningful for their work and that calculating earned value for incomplete features is misleading. The architecture team has no issues providing earned value data. How should the project manager handle this situation?