PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 2.7

PMP Practice Question: Process — Predictive, Medium

You are managing a government infrastructure project using a predictive approach. During the executing phase, a key supplier notifies you that they cannot deliver critical materials by the scheduled date due to manufacturing delays, which will impact the critical path by three weeks. The project has a fixed deadline tied to regulatory approval timelines. Your sponsor is concerned about potential penalties. What should you do first?

← All questions

Study this topic