PMP Practice Question: Business Environment — Hybrid, Hard

A financial services company is implementing a new customer portal using a hybrid approach. The predictive track focuses on regulatory compliance features with firm deadlines, while the adaptive track develops customer experience enhancements through iterative releases. During sprint planning, the product owner wants to prioritize adaptive work that would delay critical compliance features needed for an upcoming regulatory audit. The regulatory deadline is non-negotiable, and missing it would result in significant fines. Several team members argue that customer features will generate more business value. What should the project manager do?