ProcessAgileMediumECO: Process Task 2.12

PMP Practice Question: Process — Agile, Medium

An agile team working on an e-commerce platform has been using story points for estimation and tracking velocity. After six sprints, a new senior developer joins the team, and velocity increases from an average of 40 points to 55 points per sprint. The product owner is excited about the increased velocity and begins pressuring the team to commit to 55+ points each sprint going forward. However, the team's Definition of Done hasn't changed, and the scope of individual stories remains similar. What should the project manager do to address this situation?