PMP Practice Question: Process — Agile, Medium
An agile team working on an e-commerce platform has been using story points for estimation and tracking velocity. After six sprints, a new senior developer joins the team, and velocity increases from an average of 40 points to 55 points per sprint. The product owner is excited about the increased velocity and begins pressuring the team to commit to 55+ points each sprint going forward. However, the team's Definition of Done hasn't changed, and the scope of individual stories remains similar. What should the project manager do to address this situation?
Study this topic
- 📖Scope Management in Hybrid Projects: PMBOK 8 Principles
Master scope management in hybrid environments using PMBOK 8's principles-based approach. Learn how to balance structure and flexibility for successful delivery.
- 📖Critical Path Method: Mastering CPM for Project Success
Learn how to master the Critical Path Method for the PMP exam and real-world project management. Understand float calculation, network diagrams, and schedule optimization techniques.
- 🗂️Flashcards: Schedule, Estimating & Financial Formulas
14 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?