You are managing a multi-phase engineering project that is currently in month 8 of a 16-month schedule. During performance reviews, you notice that four team members who joined the project three months ago are not integrating well with the existing team. They frequently work in isolation, miss key communications, and their deliverables require significant rework. The original team members have mentioned feeling frustrated with the additional coordination effort. These four members were added to accelerate the project schedule, but productivity has not improved as expected. What is the best approach to address this situation?