PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 2.1

PMP Practice Question: Process — Predictive, Medium

You are managing a large infrastructure project using a predictive approach. During the execution phase, a key vendor informs you that a critical component will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and potentially the project's contractual completion date. The project sponsor is highly concerned about meeting the deadline. What should you do first?

← All questions

Study this topic