PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 5.2: Manage changes to the project

PMP Practice Question: Process — Predictive, Medium

You are leading a software development project using a waterfall approach. The design phase has been completed and approved by stakeholders. As the development phase begins, a key stakeholder requests a significant change to the user interface that would require redesigning several approved components. The change would add value but was not included in the original scope. The stakeholder insists this is just a clarification of the original requirements. What is your BEST course of action?

← All questions

Study this topic