PeopleAgileMediumECO: People Task 1.6

Your agile team has been working together for three months and has established a good rhythm. During sprint planning, two developers disagree about the technical approach for a critical user story. The disagreement becomes heated, with each developer defending their position strongly. The rest of the team appears uncomfortable, and the planning session has stalled for 20 minutes. Both proposed approaches are technically viable but represent different trade-offs between speed and maintainability. How should you facilitate resolution?