PMP Guide — Empowering Project Managers
Business EnvironmentPredictiveMediumECO: Business Environment Task 1.4

PMP Practice Question: Business Environment — Predictive, Medium

A project manager is executing a predictive ERP implementation project for a manufacturing company. During a steering committee meeting, the CFO announces that the company is acquiring a smaller competitor, which will add 200 employees and two manufacturing facilities within four months. The acquisition was not anticipated in the project planning. The current project scope covers only the existing organization structure. Several stakeholders immediately suggest expanding the project scope to include the acquired company. What should the project manager do next?

← All questions

Study this topic