You are managing an infrastructure project with multiple external vendors. One vendor has consistently missed milestone dates, causing delays to dependent activities. You have documented these issues and discussed them in previous status meetings. The vendor's project manager claims their delays are due to incomplete information from your team, though your records show all required information was provided on schedule. The vendor is now 10 days behind on a critical path activity. What is the MOST appropriate next step?