PMP Practice Question: Process — Predictive, Hard

You are managing a complex systems integration project with 12 external vendors and 45 internal team members. The network diagram shows 8 paths through the project, with the critical path having 14 months duration and 4 months total float across all activities. During month 6, you perform schedule compression analysis because a key stakeholder requests moving the completion date forward by 3 months. Your analysis shows: fast-tracking would create 18 new dependency relationships and increase risk significantly; crashing the critical path would cost $2.4M for a 2-month reduction; adding resources to near-critical Path B (currently 11 months with 3 months float) could reduce it to 8 months for $800K. The stakeholder has approved a budget increase of up to $1.5M for acceleration. What is the MOST effective approach?