PMP Practice Question: Business Environment — Hybrid, Medium

A financial services company is executing a digital transformation project using a hybrid approach. The predictive component involves infrastructure upgrades, while the adaptive component focuses on developing customer-facing applications. During a governance review, the compliance officer raises concerns that the adaptive team's two-week iterations may not provide sufficient documentation trails for regulatory audits, which require detailed change approval records. The project manager needs to address this compliance requirement without significantly impacting the team's agility. What should the project manager do?