PMP Practice Question: Business Environment — Hybrid, Medium

Your pharmaceutical company is executing a hybrid project to develop and launch a new drug delivery system. The project includes predictive clinical trials and regulatory submissions alongside adaptive marketing and distribution planning. Six months into the project, a global health crisis creates unprecedented demand for home-delivery medical solutions. Your executive team wants to capitalize on this market opportunity by accelerating your launch timeline by four months. The clinical trial phase (predictive) cannot be shortened due to regulatory requirements, but it's currently on schedule for the original timeline. How should you proceed?