PMP Practice Question: Process — Hybrid, Medium

Your organization is implementing a new customer portal using a hybrid approach. The compliance and security requirements are being managed predictively with detailed documentation and stage-gate approvals, while the user interface features are developed iteratively using two-week sprints. During a sprint review, stakeholders request significant changes to the authentication flow that would require modifications to the security architecture currently in the design phase. The security architect says these changes would delay the security deliverables by one month. What is the best way to handle this situation?