PMP Practice Question: Process — Predictive, Medium

You are managing a software implementation project for a financial institution using a waterfall approach. During quality testing, the QA team discovers that 12% of test cases are failing, primarily related to security authentication features. The quality management plan specified that no more than 5% of test cases should fail at this stage. The development team believes they can fix the issues within one week, but this will delay the scheduled user acceptance testing. What should you do?