During sprint planning for a software development project, your team is estimating user stories for the upcoming two-week sprint. One critical story that the Product Owner wants included has significant technical uncertainty. Three developers provide estimates ranging from 3 to 13 story points, indicating vastly different understandings of the work involved. The team has already committed to 32 story points of well-understood stories, and their average velocity is 40 story points. What should the team do with this uncertain story?