PMP Practice Question: ProcessPredictive, Hard

You are leading a construction project that is 65% complete when a key subcontractor declares bankruptcy. This subcontractor was responsible for all electrical work, representing 20% of remaining project activities. Three alternative subcontractors have been identified: Vendor A can start immediately but costs 35% more; Vendor B matches the original cost but needs 45 days mobilization; Vendor C costs 15% more and needs 20 days mobilization. The electrical work is on the critical path, and contract penalties of $50,000 per week apply after the baseline completion date, which is 90 days away. Your analysis shows current electrical work would take 70 days. What is the BEST course of action?

← All questions
📖

Study this topic

WBS Work Breakdown Structure: Proven Best Practices

Master the essential techniques for creating effective Work Breakdown Structures that drive project success and align wi

More Process Questions

View all →