PMP Practice Question: Process — Predictive, Hard
You are leading a construction project that is 65% complete when a key subcontractor declares bankruptcy. This subcontractor was responsible for all electrical work, representing 20% of remaining project activities. Three alternative subcontractors have been identified: Vendor A can start immediately but costs 35% more; Vendor B matches the original cost but needs 45 days mobilization; Vendor C costs 15% more and needs 20 days mobilization. The electrical work is on the critical path, and contract penalties of $50,000 per week apply after the baseline completion date, which is 90 days away. Your analysis shows current electrical work would take 70 days. What is the BEST course of action?
Study this topic
- 📖Earned Value Management: Your PMP Exam Formula Survival Guide
Master EVM formulas, interpret performance metrics, and tackle calculation questions with confidence. Essential Process domain knowledge for PMP success.
- 📖Risk Management in PMBOK 8: Principles for the 2026 PMP Exam
Discover how PMBOK 8's principles-based approach transforms risk management for the 2026 PMP exam. Learn essential strategies for the Business Environment domain.
- 🗂️Flashcards: Risk Responses, Reserves & Contract Types
14 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?