PMP Practice Question: Business Environment — Agile, Medium

A software development team is working in two-week sprints for a fintech startup. The company's main investor schedules a quarterly review meeting in the middle of Sprint 7 and requests a demonstration of all features completed to date. The product owner wants to stop the current sprint, prepare a polished demonstration with additional features that are 80% complete, and resume the sprint afterward. The Scrum Master argues this would disrupt the sprint and violate Scrum principles. Several team members are willing to work overtime to finish the incomplete features before the investor meeting. What is the best course of action?