ProcessPredictiveEasyECO: Process Task 5.1

You are managing a software implementation project using a waterfall approach. The testing phase has just begun, and the QA team reports that 15% of test cases are failing due to missing requirements that were not included in the requirements specification document approved three months ago. The client insists these requirements are essential. What is the best course of action?