You are managing a hybrid software project where features are developed using Scrum, but regulatory compliance reviews follow a stage-gate process. A critical sprint deliverable has been completed and tested, but it cannot be released until passing a compliance review scheduled in three weeks. The product owner wants to continue building dependent features in the next sprint. Team members are concerned this creates risk if compliance findings require rework. The compliance team cannot accelerate their review schedule. What approach best balances team empowerment with risk management?