PMP Practice Question: Business Environment — Hybrid, Easy

A manufacturing company is running a hybrid project to modernize its supply chain systems. The project uses predictive methods for replacing legacy hardware and adaptive methods for developing a new mobile app for warehouse workers. The product owner for the mobile app portion wants to review progress and provide feedback. During planning, the team established monthly steering committee meetings for overall project governance and two-week sprints for the mobile app development. When should the product owner primarily engage to review the mobile app progress?