PMP Practice Question: People — Predictive, Medium
You are managing a software development project using a waterfall methodology. During the development phase, your lead developer informs you that she has received a job offer from another company and will be leaving in three weeks. She is the only team member with deep knowledge of the legacy system integration, which is critical for the next phase. The project is currently on schedule, and this phase is expected to complete in two months. What is the most effective action to take?
Study this topic
- 📖AI in Project Management: Your 2026 PMP Exam Guide
Master AI concepts for the 2026 PMP exam. Learn how artificial intelligence impacts project management, what you need to know for test day, and practical applications.
- 📖Issue and Risk Logs: Complete Guide for Project Managers
Master issue and risk log management with proven techniques aligned with PMBOK 8th Edition. Learn how to track, prioritize, and resolve project challenges effectively.
- 🗂️Flashcards: Risk Responses, Reserves & Contract Types
14 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?