PMP Practice Question: Business Environment — Agile, Medium

Your agile team is developing a mobile banking application for a financial services company. During sprint planning, the compliance officer informs the team that new regulatory requirements have been issued by the financial authority and must be implemented within 60 days. The product owner wants to continue with the current sprint plan focused on new customer-facing features. The regulations affect data encryption and audit logging across multiple user stories. What should the agile project manager do first?