PMP Practice Question: Business Environment — Hybrid, Medium

Your organization is running a hybrid product development project for a new medical device. The hardware design follows a stage-gate predictive approach due to regulatory requirements, while the software interface is developed using Scrum. The project is progressing well when your country's health ministry announces upcoming changes to medical device certification standards that will take effect in 14 months. Your project is scheduled to submit for certification in 10 months. The regulatory affairs team indicates the new standards may require additional clinical testing and documentation. What is the best course of action?