You are managing a hybrid project with a distributed team across three time zones. The agile components use Scrum with daily standups at 9 AM EST, while the waterfall components have weekly status meetings at 10 AM EST. Team members in the Pacific time zone (6 AM and 7 AM their local time) have complained these meeting times are difficult. One team member has started skipping standups, and another has requested to send written updates instead. Productivity metrics show the Pacific team's velocity declining. How should you address this situation?