PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 3.3

PMP Practice Question: Process — Predictive, Medium

During the planning phase of a software development project, your team has identified 47 risks. You've completed qualitative risk analysis and are now preparing for quantitative risk analysis. The project sponsor questions why you need to spend additional time and budget on quantitative analysis when risks have already been prioritized. The project has a firm deadline for regulatory compliance and a contingency reserve of 10% has been allocated. What is the strongest justification for conducting quantitative risk analysis?

← All questions

Study this topic

PMP Practice Question — Process · Medium | PMP Guide