PMP Practice Question: Business Environment — Hybrid, Easy

A financial services company is developing a new mobile banking application using a hybrid approach. The infrastructure and database design follow a predictive methodology with detailed upfront planning, while the app features are developed using two-week sprints. The marketing department wants to launch a pilot program in two months, but the infrastructure team reports they need four months to complete their work according to the original plan. What is the best way for the project manager to respond?