PMP Practice Question: Business Environment — Hybrid, Hard

A global technology company is executing a digital transformation program with multiple hybrid projects across regions. Corporate strategy emphasizes agility and innovation, but a key project in a highly regulated market (healthcare) must comply with strict data sovereignty and validation requirements. The regional project team has adopted agile practices that conflict with corporate audit requirements for traceability and documentation. The compliance officer has flagged the project as high-risk, while the regional leadership argues that excessive documentation undermines agility and time-to-market. The project manager must balance corporate governance, regulatory compliance, and agile delivery. How should the project manager address this conflict?