A construction firm is executing a commercial building project using a hybrid approach. The structural engineering and foundation work follow a predictive methodology with detailed plans and sequential phases, while the interior design and tenant customization work uses an iterative approach with regular client feedback cycles. The client's real estate market conditions have shifted, and they want to explore converting some floors to a different use case. When should the project manager engage the client in detailed discussions about this change?