PMP Guide — Empowering Project Managers
ProcessPredictiveHardECO: Process Task 7.4

You are managing a government defense project operating under a Cost Plus Fixed Fee (CPFF) contract with a target cost of $8 million and a fixed fee of $800,000. At the 60% completion point, you discover that a subcontractor has been misclassifying certain labor costs as direct project costs when they should have been indirect overhead costs. The misclassification has inflated your actual costs by $400,000. The client's auditor has identified this issue and is demanding corrective action. The contract includes a clause limiting reimbursable costs to 115% of target cost. What is your most appropriate immediate action as project manager?

← All questions
📖

Study this topic

WBS Work Breakdown Structure: Proven Best Practices

Master the essential techniques for creating effective Work Breakdown Structures that drive project success and align wi