PMP Practice Question: Business Environment — Hybrid, Easy

A manufacturing company is implementing a new enterprise resource planning (ERP) system using a hybrid approach. The project team has completed three sprints for the custom reporting module while simultaneously following a predictive approach for the hardware infrastructure deployment. The finance department requests a detailed cost forecast for the next quarter to support their budget planning cycle. What should the project manager do first?