PMP Practice Question: Business Environment — Agile, Hard

Your agile team is developing a digital banking platform in a highly regulated financial services environment. During Sprint 3, a new government regulation is announced that will take effect in 90 days, requiring significant changes to customer authentication processes. The product owner wants to immediately pivot the next three sprints to address compliance, but this would delay several high-value customer features that stakeholders have been expecting. The team's current velocity suggests they cannot deliver both compliance changes and the committed features within the regulatory deadline. What should you do first?