PMP Practice Question: Business Environment — Predictive, Hard

Your organization is executing a three-year government defense project using a predictive approach with strict earned value management (EVM) reporting requirements. At the 15-month progress review, the Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.82. The customer is threatening contract termination due to poor performance. Your executive sponsor suggests re-baselining the project to show improved metrics for the next reporting period. The original baseline was approved by all stakeholders including the government oversight committee. What is the most appropriate action?