PMP Practice Question: Business Environment — Hybrid, Easy

A project manager is leading a supply chain optimization project using a hybrid approach for a global manufacturing company. The foundational process redesign is following a predictive timeline, while technology enablement is being delivered through iterative sprints. During a quarterly business review, the CFO announces that the company is facing budget constraints due to unexpected economic conditions and asks all project managers to identify areas where costs can be reduced. The project is currently meeting its planned milestones and delivering incremental value. What is the best way for the project manager to address this request?