PMP Practice Question: Business Environment — Predictive, Easy

A project manager is assigned to deliver a new customer relationship management (CRM) system for a retail company. During the planning phase, the project manager learns that a major competitor has just launched a similar system with innovative features that customers are responding to positively. The sponsor is concerned about market positioning. The project requirements have been approved and baselined. What should the project manager recommend?