PMP Guide — Empowering Project Managers
PeopleHybridMediumECO: People Task 1.1

PMP Practice Question: People — Hybrid, Medium

Your hybrid project team includes five developers working in two-week sprints and three quality assurance specialists who follow a phase-gate testing approach. The QA lead insists on a formal test plan and three-day regression test cycle after each sprint before accepting any deliverables. This creates a bottleneck, as completed sprint work sits idle waiting for QA approval while developers begin new work. Defects are often found late, requiring developers to context-switch back to previous sprint work. What is the best way to improve this situation?

← All questions

Study this topic

More People Questions

View all →
1
MediumPredictive

You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?

→
2
MediumPredictive

You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?

→
3
MediumPredictive

You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?

→