PMP Practice Question: PeoplePredictive, Hard

Your predictive project is entering month 8 of a 14-month schedule. Three team members who were critical resources for the design phase have been reassigned to other organizational priorities by their functional managers, despite your resource management plan identifying them as needed through month 10. The remaining team has the technical skills but lacks the institutional knowledge these members possessed. The project sponsor is pressuring you to maintain the original schedule. Performance reviews show current team morale is declining. What is your best course of action?

← All questions
📖

Study this topic

Will AI Replace Project Managers? The Honest Answer

Explore the realistic impact of AI on project management careers, what the 2026 PMP exam teaches about AI integration, a

More People Questions

View all →
1
MediumAgile

During sprint planning, your development team commits to 45 story points based on historical velocity. However, your product owner insists they must complete 60 story points this sprint because of a commitment made to a key stakeholder. The product owner argues that the team 'just needs to work harder' and threatens to escalate to senior management if the team doesn't comply. The team looks to you, the Scrum Master, for guidance. How should you respond?

2
MediumAgile

Your agile team has a new member, Sarah, who joined two weeks ago. Sarah has strong technical skills but comes from a traditional waterfall background. During the current sprint, you notice Sarah working in isolation, not updating the task board, and not asking for help despite her story being blocked. In the standup, she reports 'everything is fine' even though you can see she's struggling. Other team members have offered help, but she politely declines. What is the most effective way to help Sarah adapt to the agile team environment?

3
MediumAgile

Your agile team has been consistently meeting sprint commitments, but during a recent retrospective, team members admitted they have been padding estimates significantly to ensure they never miss a commitment. The team's capacity allows them to complete stories early, but they wait until late in the sprint to pull in additional work to avoid looking like they overcommitted. The product owner is frustrated because the team could be delivering more value. What should you do to address this behavior?